PROJECT:
BLUMBERG ROAD LIFT STATION
Project Overview
Construction of a 2,100 GPM Duplex Lift Station Including: excavation & installation of precast wet well structure, connect underground sanitary influent, install discharge piping & valves, connect to existing force main, protective coatings, installation of electrical and controls (ATS, Control Panel, Electrical Gear, Site Lighting, emergency back up generator), and all site work fencing, paving, & gravel road for a fully functioning lift station.
OWNER:
City of Hempstead, TX
ENGINEER:
Bleyl Engineering
notice to proceed:
02/08/2023
Project Completed:
06/21/2024
CONTRACT AMOUNT:
$811,641