PROJECT:

BLUMBERG ROAD LIFT STATION

Project Overview

Construction of a 2,100 GPM Duplex Lift Station Including: excavation & installation of precast wet well structure, connect underground sanitary influent, install discharge piping & valves, connect to existing force main, protective coatings, installation of electrical and controls (ATS, Control Panel, Electrical Gear, Site Lighting, emergency back up generator), and all site work fencing, paving, & gravel road for a fully functioning lift station.

OWNER:

City of Hempstead, TX

ENGINEER:

Bleyl Engineering

notice to proceed:

02/08/2023

Project Completed:

06/21/2024

CONTRACT AMOUNT:

$811,641