Project Overview

Construction of a fully functional lift station which includes construction of a 36’ deep, 10’ x 10’ Precast Concrete Wet Well w/ cast in place bottom & top slabs, 2 submersible pumps with discharge piping & valves, access hatches, protective coatings, control panel, automatic transfer switch, float switches electrical installation & startup, underground sanitary sewer pipe & manholes, site work concrete pavement,  emergency natural gas generator, fencing & gates.

OWNER:

B-E Development, Inc. obo Lumberton MUD

ENGINEER:

Elevation Land Solutions

notice to proceed:

11/28/2022

CONTRACT AMOUNT:

$1,079,839.92

Project Completed:

07/30/20224